Following is a list of schools, proposed projects, and estimated costs:
Bonanza, completion of roof replacement, lighting upgrade, $583,642.
Brixner Junior High, roof repair and update fire alarm system, $462,000.
Chiloquin Elementary, gym roof, update fire alarm system, $75,500.
Chiloquin Junior/Senior High, Lighting upgrade, roof with rigid insulation, replace failing aluminum window-wall panel system, remove asbestos linoleum, install VCT flooring, replace and upgrade heating and ventilation system, $2,306,000.
District office, fire alarm system, $27,500.
Ferguson Elementary, Lighting upgrade, replace window/wall system, improve heating/air quality system, roof replacement, $1,560,000.
Gearhart, fire alarm system update, $24,300.
Gilchrist Elementary, fire alarm system update, $26,615
Gilchrist Junior/Senior High, wood shop roof, fire alarm system update, $105,000.
Henley Elementary, new school with gym, cafeteria, relocated playground and parking, $19,410,000.
Henley High School, completion of lighting upgrade, $349,440.
Henley Middle School, fire alarm system update and lighting upgrade, $233,912.
Keno Elementary, fire alarm system update and completion of lighting upgrade, $172,352.
Lost River Junior/Senior High, fire alarm system update, completion of roof, $293,169.
Malin Elementary, fire alarm system update, completion of lighting upgrade, $132.782.
Mazama High School, fire alarm system update, heating control system update, $517,718.
Merrill Elementary, fire alarm system update, roof repair, lighting upgrade, $307,151.
Peterson Elementary, restroom remodel, replace windows, remove asbestos flooring, install vinyl flooring, improve heating/indoor air quality system, upgrade fire alarm system, $1,608,873.
Shasta Elementary, fire alarm system update, ceiling tile replacement, new windows, lighting upgrade, $630,983.
Stearns Elementary, Lighting upgrade, replace window wall system, remove asbestos flooring, install new flooring, new heating system, $1,449,043.
Other costs:
Lighting project engineering and contigency, $292,500.
Debt issuance cost, $300,000.
Overall contigency, $131,520.
Total, $31,000,000.